Free float bar

Joe MansourMember for 24 years 1 month
Created
4
2
0
Hello planners.

Is there a way to show the free float bar in P3. I need to show the earliest date an activity can start and the latest date it must finish without affecting the successor activities.

Joe

4 replies

Oldest first
  1. 0
    Jeffrey Huneycutt ·
    Assuming I understand you correctly...all you need to do is select bar under the format heading and add a bar with the parameters of early start and late finish.

    Jeff
  2. 0
    Paul Harris ·
    In P3 the total float and free float value are available as columns. These are calculated on the predecessor calendar, as is lag.

    A bar from the early finish to late finish is by definition the Total Float, and may be created in P3.

    A bar from the early finish of an activity to the earliest early start of all successors is the Free Float. This field is NOT available as a standard field in the P3 Bars form and therefore is not a standard option.

    A Free float bar is available in SureTrak and I use SureTrak when I am required to produce this bar.

    I also recommend any one who has P3 should also have SureTrak as it has a number of good features not available in P3.

    Regards
    Paul E Harris
    Eastwood Harris
  3. 0
    Steven Oliver ·
    However, using Custom Data Items and Excel, it would be possible to create a custom bar
  4. 0
    Jorge Taguinod ·
    1. Set a new Custom Data Item to Hold the Finish Date of the Free Float Bar. In this case, we’ll Use:

    Name = FFBR
    Type = F
    Length = 7
    Description = Free Float Bar

    2. Run this statement in a Global Change to calculate the value of FFBR:

    &TMP EQ EF + FFL
    FFBR EQ &TMP -1

    3. Create a new bar:
    Start Point = Early Finish
    End Point = Free Float Bar (the one we created in Step 1 and manipulated using Global Change in Step 2)
    Bar = Dotted Line

    Modify Endpoints and Select FFBR (found at the bottom under "Custom data item shapes and colors") Change the shape to a circle and give it a green color. Or whatever shape and color you prefer.

    4. Exit it and you’re done! If you turn on the Early Bar, Total Float Bar and Free Float Bar, then you’ll see all three.

    I tried this. It works. I hope it works for you, too.

    Jorge