P3 set up enquiry

Colin StirlingMember for 23 years 1 month
Created
1
1
0
Schedule details

P3 schedule containing up to 500 logically linked and/or constrained activities, with an hourly planning unit and a calendar based on an 8 hour shift.

Problem

When project is levelled (and scheduled), I want the software to automatically delay an activity, if it cannot start and finish in the same shift. (i.e. only 1 hour of shift available and activity is 2 hours
duration, therefore delay until next shift.)

Can anyone suggest how to set up P3 to undertake the above.

1 reply

Oldest first
  1. 0
    Mk Tse ·
    In Tools - Level - splitting, set the maximum number of splits per activity is 0
    i.e. no split allowed.