P3 set up enquiry
In the Open Standard
Colin StirlingMember for 23 years 1 month
- Created
- 1
- 1
0
Schedule details
P3 schedule containing up to 500 logically linked and/or constrained activities, with an hourly planning unit and a calendar based on an 8 hour shift.
Problem
When project is levelled (and scheduled), I want the software to automatically delay an activity, if it cannot start and finish in the same shift. (i.e. only 1 hour of shift available and activity is 2 hours
duration, therefore delay until next shift.)
Can anyone suggest how to set up P3 to undertake the above.
P3 schedule containing up to 500 logically linked and/or constrained activities, with an hourly planning unit and a calendar based on an 8 hour shift.
Problem
When project is levelled (and scheduled), I want the software to automatically delay an activity, if it cannot start and finish in the same shift. (i.e. only 1 hour of shift available and activity is 2 hours
duration, therefore delay until next shift.)
Can anyone suggest how to set up P3 to undertake the above.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?