rebaseline

Forum GuestMember for 17 years 8 months
Created
6
1
0

how does primavera rebaseline when tracking project

i want to understand how p3 resolve the problem of new BQWS with the BQWP

you know that when you want to re-baseline a project
you must to put BQWS=BQWP

i want to know how p3 do that

is it with " GLOBAL CHANGE" or something else

i’m here for more explications

thank for your help

6 replies

Oldest first
  1. 0
    Mk Tse ·
    by global change to update the required field(s).
  2. 0
    Forum Guest ·
    please more explications
  3. 0
    Zq qz ·
    Another method is Update Target Option
  4. 0
    Mk Tse ·
    Make use fields, like custom data fields, to store some calculated values in step by step calculation.
    The whole process is control by global change.
  5. 0
    Bensouyah Mohamed ·
    next time i’ll give u a real example of project
  6. 0
    Zq qz ·
    Another method is using your current schedule as your target