Jose Valdez MarcosMember for 25 years 5 months
Created
1
1
0
Hi All,

I work in an Engineering company. I have created a Level 3 schedule in P3 with the engineering deliverables (drawings)as my activities. I created in P3 a custom data for the drawing nos. (20 characters). I am also using our company software "InControl". My question is, can you create an activity code in InControl that corresponds to P3 Activity Id (10 characters)? I can then export these data to P3 to update my schedule progress and actual dates. Appreciate if you can help me sort out my problem.

Thanks,

Joe Marcos
PP 420

1 reply

Oldest first
  1. 0
    Luca Basile ·
    I do not know what You can do with InControl, but in the case You are able to put with coding (that will reflect the P3 ID), using RA engine You can update automatically Your P3 schedule.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?