% Complete difference
In the Open Standard
Jerome OdehMember for 22 years 8 months
- Created
- 3
- 1
0
In my schedule, the % Complete weighting is based on Cost(Tools>Option>Summarisation) and when I run the schedule it shows 50% Complete. But when I read the Scheduling Report produced in Primavera Look, it showed 48.9% complete.
Interesting, if I change the % Complete weighting to Duration, my schedule shows 49% which tallies with Primavera Look Report’s 48.9%.
How can I get the Scheduling Report generated in Primavera Look to also calculate & display % Complete based on Cost like my schedule?
Interesting, if I change the % Complete weighting to Duration, my schedule shows 49% which tallies with Primavera Look Report’s 48.9%.
How can I get the Scheduling Report generated in Primavera Look to also calculate & display % Complete based on Cost like my schedule?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?