Import from WKS or DBF
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 12
- 3
0
I have problem in importing to P3 from WKS and DBF.
Total no of activities in P3= 12K. Exported 1000 activites to dbf and imported it after updating the progress. Around 10% of my actuals were missing. In the past weeks I didn’t have an problem. It just happened this week.Import function didn’t account those activities. Did any one come accross such import problem?. Any advise?.
Thanks.
Total no of activities in P3= 12K. Exported 1000 activites to dbf and imported it after updating the progress. Around 10% of my actuals were missing. In the past weeks I didn’t have an problem. It just happened this week.Import function didn’t account those activities. Did any one come accross such import problem?. Any advise?.
Thanks.
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?