How to assign resources to completed activities

Forum GuestMember for 17 years 8 months
Created
1
1
0
Hi Guys,

How to assign resource to completed activities.

Thanks & regards

Kumar

1 reply

Oldest first
  1. 0
    Forum Guest ·
    Just open the resources form and add the quantity in to the budgeted quantity, but not into unite per day!