P3SDEF conversion - not carrying decimal places???

Forum GuestMember for 17 years 8 months
Created
2
1
0
This is very strange and it’s the first time I’ve seen this happen. I’m working on a Corps of Engineers project and have to submit the schedule SDEF data file each month with the schedule update. Some of the activities each month carry dollars and cents for earnings to date. When I do the P3SDEF conversion only two or three activities will carry the decimal places, all the others will be rounded off to the nearest whole dollar amount for both Budgeted Cost and Earnings to Date. This is only in the SDEF text file after the conversion, the P3 schedule calculates and carries the decimal places correctly.

Has anyone ever run into this problem before? I’ve checked the activities codes and their affects on the output file but can’t find any solutions.

Brian Cass
CF Jordan, LP
P3 v3.1

2 replies

Oldest first
  1. 0
    Forum Guest ·
    Figured it out. SDEF will round off all budgeted costs and/or earned value amounts that are greater than 7 digits including decimal places (i.e. anything over 99,999.99 will be rounded off to whole dollars.) If anyone knows a patch that will correct this, please let me know. It’s a pain manually correcting the SDEF output files especially when you’re scheduling eight different projects.
  2. 0
    B Cass ·
    Sorry, I was logged in as Forum Guest when I posted these two.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?