Merged Projects

Forum GuestMember for 17 years 8 months
Created
3
1
0
Can we interrelate activities / level resources / have Look reports of the merged projects

3 replies

Oldest first
  1. 0
    Mk Tse ·
    To certain extend, it is possible. Please let us have more information on your requirement
  2. 0
    Forum Guest ·
    Dear .mktse,

    Thanks for your response. I will like to link ceratin activities between the projects owing to sequence requirements
  3. 0
    Mk Tse ·
    Sorry for the late response.
    For the interlink between/among projects, there is some limitations.
    No. of relationship cannot more than ?? (I forget the number, around 30 only)
    Check the option in Schedule - Advance Option, take those interlinks in scheduling
    For resources part, I have no experience but definite only one resource pool will be refer to.