I have made wbs for a project as under:
1. Construction of Building
2. Phase 1
3. phase 2
4. Externat Works

My problem is that when I organize Level I with TOTAL the Final date is only shown of WBS 1,2 and 3 without Externatl Works Final date?

Why this happens? Why External Final date is not shown in Level total?

Please suggest me a way so that Level cover whole 1,2,3 and 4 wbs dates:

Its urgent plz

10 replies

Oldest first
  1. 0
    Mk Tse ·
    According to your listed, all 4 items are in Level 1.
    would you mind list the WBS value aginst the item for futther details
  2. 0
    Mk Tse ·
    According to your listed, all 4 items are in Level 1.
    would you mind list the WBS value against the item for futther details
  3. 0
    Mk Tse ·
    According to your listed, all 4 items are in Level 1.
    would you mind list the WBS value against the item for further details
  4. 0
    Mk Tse ·
    (Sorry for the duplicated postings since a book falls on the keyboard when I editing.)

    Consider the WBS as follows: -
    1. Construction of Building
    1.1 Phase 1
    1.2 Phase 2
    1.3 External Works
  5. 0
    Jaco Stadler ·
    Have a look at your wbs Structure I think the problem is there.

    Standard P3 setting will not allow this to work correct. (10)

    Data - WBS - Structure

    Also remember to look at organize and total at the different levels
  6. 0
    Rafael Davila ·
    Try organizing first by Project with totals then by WBS. In this way (organizing by activity codes) you make sure you are adding a level above all WBS codes, totals will roll up to the project level. If this works then check on your WBS structure.
  7. 0
    Shahzad Munawar ·
    Hi John

    In my view your WBS coding and defining is not correct which needs to be reviewd that’why when you organize, it does not cover the FINAL date of whole project.

    Moreover send me your copy of P3 file for correcting this error.

  8. 0
    Dayanidhi Dhandapany ·
    Dear John,

    Send a copy of your program to plannerdaya@yahoo.com, let me have a look.

    Regards

    Daya
  9. 0
    Steven Oliver ·
    There are some spreadsheets (activity.xls) provided with the P3 installation CD, which with a bit of tweaking would let you do this.


    HTH


  10. 0
    Frank Borcherdt ·
    Can also update activities using Global Change i.e. SS(WBS,x,y) where x is start position including the separators and y is length.

    To update the dictionary see knowledge base article 200252492644 and use Project.xls to export the WBS codes and tiles, then massage this to conform to a previously saved activity code format and then import the activity codes and titles.

    Work in a copy or make sure you have good backups before you start.