Large Program / Multiple Schedules
In the Open Standard
Ben WaltersMember for 22 years
- Created
- 12
- 4
0
I’ve been tasked with creating a master schedule for a $1B+ (US) project where all engineers and contractors will be required to submit schedules in Suretrak/P3 formats on a monthly basis. Our intent is to be able to receive updates on a monthly(+/-) basis and determine the project’s status without re-keying any of the information.
What is the best way to organize this? Early on, I was supplied with Suretrak and created a folder structure similar to the following:
C:Master
C:MasterRD "Phase 1 Road Design"
C:MasterRC "Phase 1 Road Construction"
C:MasterWD "Phase 1 Site Design"
C:MasterWC "Phase 1 Site Construction"
This appeared to work for awhile using Suretrak’s project groups, but once in a rush I did File | Save as and I believe that basically copied the schedules to the main folder.
Recently I was upgraded to P3 3.1 which I used several years ago, but I’ve never worked with groups or on such a project, I’ve always "traded" the schedule back and forth with either the engineer, contractor or client on a pre-determined basis.
Is it better to try and seperate the projects or just dump in one folder? We’ll have 10 to 15 schedules to update monthly at our peak and maybe 80 total during the course of the 15-20 year program.
Thanks in advance for your advice/prayers.
Ben
What is the best way to organize this? Early on, I was supplied with Suretrak and created a folder structure similar to the following:
C:Master
C:MasterRD "Phase 1 Road Design"
C:MasterRC "Phase 1 Road Construction"
C:MasterWD "Phase 1 Site Design"
C:MasterWC "Phase 1 Site Construction"
This appeared to work for awhile using Suretrak’s project groups, but once in a rush I did File | Save as and I believe that basically copied the schedules to the main folder.
Recently I was upgraded to P3 3.1 which I used several years ago, but I’ve never worked with groups or on such a project, I’ve always "traded" the schedule back and forth with either the engineer, contractor or client on a pre-determined basis.
Is it better to try and seperate the projects or just dump in one folder? We’ll have 10 to 15 schedules to update monthly at our peak and maybe 80 total during the course of the 15-20 year program.
Thanks in advance for your advice/prayers.
Ben
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?