Limited Activities in P3

Mohsin FarooqiMember for 22 years
Created
6
1
0
hi iam using p3 and i was unable to add activitys after 60 activities and iam getting an error message that activity limit excedded .can u plz help me guys

6 replies

Oldest first
  1. 0
    Mk Tse ·
    Which P3 version have installed?
    For version 2.0 demo version or acedamic version, there is limitation on number of activities and other functions.
  2. 0
    Ronald Winter ·
    You definitely are using the inexpensive academic version of P3 that is designed only for teaching. It is designed to work this way. If you want to be able to add in more than 60 activities, then you will need to purchase a full version from a Primavera Representative. Good luck!
  3. 0
    Mohsin Farooqi ·
    Hi
    Iam using p3 version 3.0 and iam not using a academic or trial version anyways thanxs for replying me
    regards
    mohsin
  4. 0
    Dayanidhi Dhandapany ·
    If it works only for 60 activities or so, then definitely it will be a demo version..........
  5. 0
    Mk Tse ·
    If your P3 is version 3.0, I strongly recommend to reinstall the software, may be more serious is install the software on other machine rather the current one.

    I remember a case that acedamic version is installed and removed. However, some installed information cannot remove from the registry due to some policies setting, all later version installation are not successful,
  6. 0
    Mohsin Farooqi ·
    you people might be right. well i was using the academic version of p3 thats why i was limited to 60 activities
    thanx any way in solving my problem

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?