I am currently working on a tender where the client states
" The employer has selected the use of Primaverea Teamplay Version 4 software to contain and manage the programme information"

I am preparing a tender programme for the project which is circa £200m in the uk with 4 separate sites, all sites running concurrently. The project is esentially traditional construction Concrete and steel frame containing a process operation.

I would normally use either Power Project 8, suretrak or P3, can anyone advise on the compatiblity of the above with Teamplay.

Thanks Andy

1 reply

Oldest first
  1. 0
    Bernard Ertl ·
    Hi Andy, you should re-post this in the Primavera Teamplay forum.

    Bernard Ertl
    eTaskMaker Project Planning Software

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?