I am looking for a method to add columns to a P3 programme. I know I can use Custom Data Items but I would require more than eight. I wish to enter numeric/% figs in these columns.
IE Data from 2 weekly updates.
Regards,
George

2 replies

Oldest first
  1. 0
    Andrew Podolny ·
    The most obvious way is to export P3 activities to Excel or Lotus and then add as much columns as you want. Another option - for advanced users who are familiar with DB design is to use InfoMaker.
  2. 0
    George Stewart ·
    Many thanks, I already do that but I wanted to be able to display these on the P3 layout.
    George