P3 Expert opinion awaited- priority please
In the Open Standard
Jimmy robertMember for 22 years
- Created
- 10
- 2
0
A schedule of 2000 activities was prepared.
It was properly linked
After schedule, following message has been found.
"Loop(s) detected - schedule run terminated"
why this message come if schedule is properly linked?
where is the fault?
Please advise. what the corrective mearuse which I make so that i run this schedule (F9) - its urgent.
It was properly linked
After schedule, following message has been found.
"Loop(s) detected - schedule run terminated"
why this message come if schedule is properly linked?
where is the fault?
Please advise. what the corrective mearuse which I make so that i run this schedule (F9) - its urgent.