New icon on tollbar

Aydin ValiyevMember for 21 years 6 months
Created
1
1
0
It’s obvious that we can add new buttons to the toolbar from Tools-Options-Toolbar. If scrool down on "Toolbar configuration" window, there are 8 buttons to each one you can assign new functions. First button works by defoult for opening "Check in-check out" window.

I would like to assign following sequence to a second button : "Tools-Tabular Reports-Resource-Loading" and "Tools-Project Utilities-Import" to third button.

I found following code for the fisrt button in P3 text file:

[Applications]
App1=Project Check-in/Check-out
Cmd1=C:\P3WIN\P3PROGS\P3CHKOUT.EXE

But don’t know how to modify as I desire. Is that possible?

P.S. And second question, but not so much important: Scroll up and down in my P3 works only if I drag down and up. How to make it work from mouse scroll wheel?

1 reply

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Hi Aydin, The 8 buttons you saw in Toolbar Configuration are to launch the .EXE, .COM or .BAT extension files from P3. You can configure all those files in P3.INI upto 8 applications. To add icon for Tabular Reports, open Toolbar Configuration > highlight Report Production icon > Insert > OK. Regards.

Log in or join to reply