Time Impact Analysis using P3
In the Open Standard
Kashyap MothaliMember for 21 years 6 months
- Created
- 2
- 2
0
I am currently reviewing a P3 as-built schedule (for the Owner) in order to evaluate a time impact that the Contractor is claiming. Is there an accepted industry standard of performing this TIA?
In order to arrive at my conclusions, I have so far used
1) Window Analysis
2) As-Built Data (based on historic daily work sheets)
Using the above options, the results (actual delay)are fairly close to each other.
The Contractor is asking for twice the time than that in my findings. Therefore, just to back my case, could anyone suggest an alternative tested/acceptable/proven method of doing a TIA?
Thanks,
Kashyap
In order to arrive at my conclusions, I have so far used
1) Window Analysis
2) As-Built Data (based on historic daily work sheets)
Using the above options, the results (actual delay)are fairly close to each other.
The Contractor is asking for twice the time than that in my findings. Therefore, just to back my case, could anyone suggest an alternative tested/acceptable/proven method of doing a TIA?
Thanks,
Kashyap
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?