P3 activities to be as MS outlook Tasks

Vamsi KolliboinaMember for 25 years 1 month
Created
1
1
0
Hi All,
There is a request/requirement to syncronize P3 project activities(on a periodical basis)with MS outlook Tasks.

Does anyone know how to go about it?Is such kind of thing possible? Would like to know the methodology/Process involved,if it can be done.

Cheers,
Vamsi

1 reply

Oldest first
  1. 0
    Mk Tse ·
    Just brainstorm on the requirement.
    From P3, export the activities into spreadsheet. Then on Outlook, import the spreadsheet into Task.
    I think mapping may required. May not possible to sync the task, overwrite may consider.