Tracking changes

Yves TrudelMember for 21 years 2 months
Created
3
1
0
Hi every one,
I’ve been trying pretty hard lately to compare progress between target project and actual one and I still cannot.
I tought I could show target Resource percent complete and Resource percent complete, then substract one from the other thru Global change after creating a custum data item, and finally filter all lines not equal to 0.
I cannot get a Target resource percent complet in the Global change dialog box, so I’m stopped.
Any solution?
Thanks in advance

3 replies

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Yves,

    Export the Target Resource % Comp, Current Resource % Comp and Custom Data Items to spreadsheet(.WK1) file or database(.DBF) file.
    Do the necessary changes and import back to P3.
    Then filter according your requirement.

    HTH
  2. 0
    Sunil Kumar ·
    Try This, Make a copy of yourr target programme and have a update done by clicking tools update progress. This gives you the percentage on your target programme or the planned percentage as on data date. Use this file as your taget in your update programme. Compare the progress of your target which is planned vs your updated progress.

    Trust this helps

    sunil
  3. 0
    Yves Trudel ·
    Thank you both,
    I will try your 2 solutions
    Regards
    Yves