unit price for resorce- HOW can I print ?

Onur OzerMember for 21 years 1 month
Created
6
2
0
Hi All,

In Report Writer (ver_p3.1) Content section-Data Item :

from Resource/cost data :

i could not find "price/unit" ? . Can’t I see that item or is there any other solutions for print all the resource dictionary .

I know resource dictionary print button . But I only want in my project (about 800 resources) in excel sheet in a column resource names and in b column resouce price per unit values . That button print a report but i don’t want that format, since i cannot get the price per unit value near the resource name .

everything is there but i cannot see price per unit data item, it must be hidden but i cannot find,

Please help at my 1st question :)

6 replies

Oldest first
  1. 0
    Raja Izat Raja Ibrahim ·
    Hi
    create a column....suggest use global change? I hope u fimiliar with global change... so i dont have to explain detail. Any how if needed...no problem. Just ask
  2. 0
    Raja Izat Raja Ibrahim ·
    Sample global change..
    Free Image Hosting at www.ImageShack.us
  3. 0
    Onur Ozer ·
    Hi Raja,

    Price per unit in our project is not Budgeted Cost divided by original duration . In our project although i changed the original duration our resource price per unit keeps its original value what we wrote before in the res.dictionary .

    I want the values in the resource dictionary

    Thanks
  4. 0
    Raja Izat Raja Ibrahim ·
    Hi,
    i already send the ammended formula, u can use straight away, or u can send me your file i can repair it for u.
  5. 0
    Giannis Kostis ·
    Hi Onur,
    In order to get Resource Dictionary and Resource Unit Prices in excel format I suggest you to use project.xls (you can find it in P3 cd-rom \Support\UTILS\EXCEL\).

    Regards
    Giannis
  6. 0
    Venkatasubramanian Ravi ·
    I have the same kind of problem.
    In my project schedule, when they created, entered the resources (manhour, = BQ*productivity) and BQ in the resources itself. They have given different names for the resources and differrent names for BQ also. I want to a show seperate column to show the resource name, manhour and the same for BQ also. Experts please in details as I am not much familier with p3.

    Thanks

Log in or join to reply