prmbatch
In the Open Standard
Gün GöksuMember for 21 years 6 months
- Created
- 3
- 1
0
Hello,
I have for the last 2 days tried to import some files with the batch utility found under the P3 CD.
I have read all of the manuals I could find. and looked at the examples but still cant get this thing to work.
this works.
PROJ L3V4 GENERATE GOKSU
GENERATE ALL L3V4 INTO D:\P3\Batch\BACH.OUT
PROJ L3V4 END
but this does not.
PROJ L3V4 TITLE DATA GOKSU
WBST 1 CONTRACT 1
WBST 11 CONSTRUCTION & COMMISSIONING
WBST 1101 CONSTRUCTION (UTILITY) PHASE-I
WBST 110101 PHASE-I UTILITY (UTIL)
WBST 11010101 CIVIL
WBST 1101010101 Civil Work for PR
WBST 1101010102 Civil Work for Equipment Foundation
WBST 1101010103 Civil Work for Building & Shelters
WBST 1101010104 Civil Works for U/G Pipes
RETURN
PROJ L3V4 END
Why?
I am trying to update the WBS dictionary.
I dont get any errors in the gen.out or P3.out files.
similarly this does not work too.
PROJ L3V4 UPDATE GOKSU
ACTVAONC1K0720 Utlt:Complete Civil Works 40
ACTVAONC1L0230 Utlt:Complete Steel Structure Work 40
ACTVAONC1M0090 Utlt:Access for Elect Space Pit(PSS-400/FAR3) 40
PROJ L3V4 END
why????
I am going nuts.
I have for the last 2 days tried to import some files with the batch utility found under the P3 CD.
I have read all of the manuals I could find. and looked at the examples but still cant get this thing to work.
this works.
PROJ L3V4 GENERATE GOKSU
GENERATE ALL L3V4 INTO D:\P3\Batch\BACH.OUT
PROJ L3V4 END
but this does not.
PROJ L3V4 TITLE DATA GOKSU
WBST 1 CONTRACT 1
WBST 11 CONSTRUCTION & COMMISSIONING
WBST 1101 CONSTRUCTION (UTILITY) PHASE-I
WBST 110101 PHASE-I UTILITY (UTIL)
WBST 11010101 CIVIL
WBST 1101010101 Civil Work for PR
WBST 1101010102 Civil Work for Equipment Foundation
WBST 1101010103 Civil Work for Building & Shelters
WBST 1101010104 Civil Works for U/G Pipes
RETURN
PROJ L3V4 END
Why?
I am trying to update the WBS dictionary.
I dont get any errors in the gen.out or P3.out files.
similarly this does not work too.
PROJ L3V4 UPDATE GOKSU
ACTVAONC1K0720 Utlt:Complete Civil Works 40
ACTVAONC1L0230 Utlt:Complete Steel Structure Work 40
ACTVAONC1M0090 Utlt:Access for Elect Space Pit(PSS-400/FAR3) 40
PROJ L3V4 END
why????
I am going nuts.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?