Eraned Value Caluculation- important
In the Open Standard
James ThorpeMember for 21 years 1 month
- Created
- 4
- 2
0
My budgeted cost of an activity is US$ 70.
Upto data date we planned to achieve 50 % i.e we should have spent US$ 35 but our actual progress is 15% which means we should spend only US$ 16 but we spent US$ 25 which means there is loss.
Please tell me How to make EV analysis for above situation on basis of weighted or equivalent basis
or on basis of
64%, 95 %
Upto data date we planned to achieve 50 % i.e we should have spent US$ 35 but our actual progress is 15% which means we should spend only US$ 16 but we spent US$ 25 which means there is loss.
Please tell me How to make EV analysis for above situation on basis of weighted or equivalent basis
or on basis of
64%, 95 %
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?