Scope changes and P3

Vanessa MorrisMember for 21 years 3 months
Created
2
1
0
Hello, when a project is underway you have your target a current schedule. How do you deal with scope changes, additional/extra works with your schedule in P3. Do you add this new activities into your current schedule? Thanks.

2 replies

Oldest first
  1. 0
    Raja Izat Raja Ibrahim ·
    hi vanessa
    if we looked at the contract, if the activities is out from the scope we add under title VO or addtional scope but if it is activities lefted behind u can see at below post how u going to add activities.
    Forum
    Primavera Project Planner - P3
    -Update target Function
  2. 0
    Charleston-Joseph Orbe ·
    Hello Vanessa,

    Yes, you have to include the changes in scope of work, variation order, etc., in your schedule.

    Generally, if you are using Work Breakdown Structure, you will add a new WBS- 50.000 Variation Order, Changes, etc. You can further make a new sub-level: 50.100 Provisional Variation Order, 50.200 Extension of Time (in case you will be going into extension of time, etc.

    The above is an example only. I hope it help you.

    Cheers,

    charlie