Updations in P3/ P3e

Dattatreya PadharthiMember for 23 years 6 months
Created
3
1
0
while updating the schedule/ activities/milestones thru Primavera Post Office,the prd file is not organised in the same way as if on the screen. which makes it difficult for discipline engineers to identify & update.
Any suggestions on that

3 replies

Oldest first
  1. 0
    Mk Tse ·
    I think it depends on the grouping, sorting order when creating the dataset. Post office cannot change the created order.
  2. 0
    Dattatreya Padharthi ·
    I do agree with that, but the way in which the discipline engrs are accustomed to (Organised as Unit-->Area-->type--> ). This becomes confusing for them.
    this sort of organsing capability is not available in Post office.

  3. 0
    Mk Tse ·
    Create coding structure for this purpose. Hope help