Hi all
Is there a way to inter -ve value for unit price or for budget to use it in retention in p3 to creat a payment.
thanks

1 reply

Oldest first
  1. 0
    Gordon Blair ·
    Ayman,

    Probably wiser to have a separate item for the retention payment.

    i.e.

    Total Price = £100000

    Activity A Budgeted Cost £85000
    Retention Payment £15000

    HTH,

    Gordon