Dear Friends
is it possible to give another colur to the summary bars (sub total bars)

12 replies

Oldest first
  1. 0
    Peter Bailey ·
    Try ’format - bars’ and then change the colours as you like them
  2. 0
    Hemanth Kumar ·
    dear peter
    you cant format summarised bars
  3. 0
    Philip Jonker ·
    Then try using hammocks, which you can format
  4. 0
    Hemanth Kumar ·
    hammock cant show real summarised % complete
  5. 0
    Sen Moc ·
    Question:

    Is it possible to give another colur to the summary bars (sub total bars)?(/i>



    Answer:

    YES. Go to Format Bars/Pattern.



    Cheers!
    Sen


  6. 0
    Hemanth Kumar ·
    Not Possible ,Pattern Will Give Color to coded activities
    Only
  7. 0
    Shahzad Munawar ·
    Not possible so far
  8. 0
    Philip Jonker ·
    You have lost it
  9. 0
    Hemanth Kumar ·
    Not Possible
    ,,,thanks to all
  10. 0
    Alex Wong ·
    Cannot unless you are using P3e teamplay or P3e/c
  11. 0
    Sen Moc ·
    Kumar,

    Create dummy activity codes (or use your existing codes).
    Then choose whatever color you prefer in Format Bars/Pattern.

    This is the only way your problem will be solved!

    Regards,
    Sen
  12. 0
    Alex Wong ·
    Or as Philip suggested using hammocks is your only way out

    However, it involved a lots of work

    Good luck

    Alex