Time Phased Data
In the Open Standard
Steve KinnaneMember for 25 years 1 month
- Created
- 4
- 1
0
When I run the resource loading report "RL-03 Resource Loading Activity Summary" from
Tools->Tabular Reports->Resource->Loading
I find that the results are not consistent and vary depending on the format of output that I select.
1) The values shown within the total column appear to be divided by a factor of 10
2) The totals of time phased data does not match the correct total amount
3) If I compare with a tabular report for the overall project I get a different profile of usage.
What is going on. Is there something I am ovelooking or is this a flaw in P3?
Tools->Tabular Reports->Resource->Loading
I find that the results are not consistent and vary depending on the format of output that I select.
1) The values shown within the total column appear to be divided by a factor of 10
2) The totals of time phased data does not match the correct total amount
3) If I compare with a tabular report for the overall project I get a different profile of usage.
What is going on. Is there something I am ovelooking or is this a flaw in P3?
4 replies
Oldest firstLog in or join to reply