Dear mohamed

Can you tell me how can work between primavera project planner p3.1 ane Exeel sheet..

Thanks

Engineer Yousf A.Ayal

1 reply

Oldest first
  1. 0
    Dattatreya Padharthi ·
    Dear Yousuf,

    I normally export the data in a *.dbf format, open that in Excel, use the data as required, change the values for importing as required , save it in a *.dbf format.
    Import back the file in excel. Though I have encountered some limitations in no of records for this exercise.
    I managed 500-550 records/ per transaction through a single file.

    Cheers
    Dattatreya