Autocost Rules
In the Open Standard
Chris MurrayMember for 22 years 7 months
- Created
- 2
- 1
0
All,
For some reason I can’t get this to work.
Quite simply all I want to do is to increase the duration of an activity then the budgeted quantity of the resouce increase accordingly.
E.g.
Duration 40d
Resource 40days work
Change:
Duration 42d
Reource to increase 42 days work i.e. Unit per day to stay at 1!!
Any help with the rules?
CM
For some reason I can’t get this to work.
Quite simply all I want to do is to increase the duration of an activity then the budgeted quantity of the resouce increase accordingly.
E.g.
Duration 40d
Resource 40days work
Change:
Duration 42d
Reource to increase 42 days work i.e. Unit per day to stay at 1!!
Any help with the rules?
CM
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?