All,

For some reason I can’t get this to work.

Quite simply all I want to do is to increase the duration of an activity then the budgeted quantity of the resouce increase accordingly.

E.g.
Duration 40d
Resource 40days work
Change:
Duration 42d
Reource to increase 42 days work i.e. Unit per day to stay at 1!!

Any help with the rules?

CM

2 replies

Oldest first
  1. 0
    Joao Ribeiro ·
    You may check "freeze units per time period" on, but be aware that it will apply to all activities.

    Cheers.
  2. 0
    Chris Murray ·
    Excellent!!

    Thank you very much!!!