Hi Everyone,
I use the batch system on a regular basis for forensic analysis, but have always had the following problems, can anyone help?
1. When using the Copy and Rename function P3 produces lock files - this has meant that we always run the analysis on a network - allowing time for the lock files to remove themselves before we copy and rename again. Can you stop P3 from producing lock files?
2. Is it possible to "Change Directory" after you have copied a Network - and then "paste" the new network (Rename) in the new directory.
3. When using the batch to schedule - how do you tell it to schedule on Retained Logic / Progress Override - when the Network default is the opposite?
4. Is there a batch command that can run multiple batchs?
Many thanks,
Paul
I use the batch system on a regular basis for forensic analysis, but have always had the following problems, can anyone help?
1. When using the Copy and Rename function P3 produces lock files - this has meant that we always run the analysis on a network - allowing time for the lock files to remove themselves before we copy and rename again. Can you stop P3 from producing lock files?
2. Is it possible to "Change Directory" after you have copied a Network - and then "paste" the new network (Rename) in the new directory.
3. When using the batch to schedule - how do you tell it to schedule on Retained Logic / Progress Override - when the Network default is the opposite?
4. Is there a batch command that can run multiple batchs?
Many thanks,
Paul
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?