ACT ID INCREMENT

Rodel carmeloMember for 21 years 5 months
Created
2
18
0
Hi Guys,

Is there an option to use global change to my problem? This will took more time to edit manually. I have an existing 3,000 activities just for instance stated below.

CCP2-0010
CCP2-0012
CCP2-0015
CCP2-0018
CCP2-0020

I want an increment of 5 and will be converted into

CCP2-0010
CCP2-0015
CCP2-0020
CCP2-0025
CCP2-0030

Any evocation and annotations from the P3 expert.

Thanks in advance...

Rodel

2 replies

Oldest first
  1. 0
    Paul Harris ·
    I would suggest you copy the project, delete the activities, then copy the activities from the old project and paste into the new and select the increment you require when pasting.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Jorge Taguinod ·
    Pare,

    [English only, please. The Moderator.]

    Note: Back up your project first!

    1. Select all activities and COPY.
    2. Delete all Activities.
    3. Paste using Auto Increment.
    - set the starting number.
    - set the increment.



    Best,

    Jorge