Resource Report by Activity

Rajeev KumarMember for 23 years 5 months
Created
1
1
0
Hi All,

Is there a standard report similar to the resource window, for each activity, just the budgeted quantity would be fine.I know there is a way by Matrix reports, but for than 30 resources, is there a simpler and easier way to tabulate all the budgeted quanity for each resource against all activities or selection of activities?

Thanks

1 reply

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    you can use matrix report format to create it. If you Insert the "TTL(item) in the matrix report format column, you can get the resources title, so that you can find easy to read the resources description in full against each resource ID.
    The otherway is to export all summarized resources to excel sheet and create the required report.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?