Resource Histogram - Primavera Project Management

Dinesh KumarMember for 20 years 5 months
Created
2
1
0
Dear All

I’m using Primavera Project Management Rel 4.1. How can I Print Resource histograms out. Can somebody help, Please.

Regards
Dinesh

2 replies

Oldest first
  1. 0
    Julie Scully ·
    Hi Dinesh

    You will need to be displaying the histogram in your activities view, then go to Page Setup -> Options -> and check the "Profile" box. If you want to print only the histogram you will need to uncheck all other options.

    Cheers
    Julie
  2. 0
    Dinesh Kumar ·
    Thanks Julie...