Anyone know how to filter for the Driving Path of any given task?

I just want to see the driving predecessors on a task.

Thanks

2 replies

Oldest first
  1. 0
    Jaime Linchangco ·
    Hi Roy,

    First way is filter the schedule based on "Longest Path" EQ Yes.

    Second way, group your activities by Total Float. This work fairly well if you are using a single calendar ID.

    Hope this work for you.

    Cheers!

    Jaime
  2. 0
    Bijaya Bajracharya ·
    Press the predecesor button (either from toolbars or from inside the activity details). You will see the list of activities which are predecessors to your activity. Check the list carefully. Immediately after activity ID column, there is a small column with no title. All the driving predecessors will have a star (*) in this column.