S-CURVES IN MS PROJECTS

Julian CoetzeeMember for 20 years 4 months
Created
2
2
0
Good Day

I am working in MS, I want to generate S-curves. After you have applied the relevant resources, I am correct by saying that you then go to the task usage sheet, roll up your tasks to their summaries, copy and paste the sheet in excel. In Excel, you then do the necessaries (totals etc, accumulatives etc) and then plot your graph?

Furthermore, is there a quicker way or better way to do this?

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    it is quicker and easier to export ’Time-phased data’ to Excel.
    Display the Analysis tool bar to get the appropriate tool.
    Regards
  2. 0
    Julian Coetzee ·
    Thanks once again Alexander! I will give it a bash!