Hello all;


Could any one please tell me the difference between task
activities and hammock activities?

Regards,

Marcio Eduardo.

4 replies

Oldest first
  1. 0
    Praves Suppa ·
    Hello,

    I found one article explained clearly for Hammock

    1. P3 calculates the duration of a hammock activity and graphically presents it on the layout
    based on the early dates only.
    2. For a hammock activity with no progress, P3 calculates a hammock’s duration by the
    difference from the earliest early start date of the its predecessor activities to the latest early
    finish date of its successor activities. Therefore it has no fixed duration. P3 calculates the
    original and remaining durations automatically based on the following formula:
    a. Original Duration = (Early Finish Date – Early Start Date)
    b. Remaining Duration = Original Duration
    3. A hammock should have at least one predecessor and one successor. A hammock without
    predecessor starts on the data date, and that a hammock without successor ends on the
    project completion date.
    4. For a hammock activity in progress, a hammock activity bar starts on the actual date, and
    P3 calculates the original and remaining durations, and percent complete automatically
    based on the following formula:
    a. Remaining Duration = (Early Finish Date – Data Date)
    b. Original Duration = (Data Date – Actual Start) + Remaining Duration
    c. Percent Complete = (Original Duration – Remaining Duration) / Original Duration
    5. A hammock activity can’t drive (push out) any task activities. I often call its behavior like a
    “Rubber Band” as it is stretched or compressed according to its successor and predecessor,
    not the other way around.
    6. If you unlink the remaining duration and schedule percent complete in the Autocost Rules
    window, you can manually enter the percent complete for a hammock activity. However,
    you absolutely can’t manually enter the original and remaining durations. P3 will overwrite
    your inputs.
    7. An asterisk mark (*) will always be shown right next to the original and remaining durations
    of a hammock activity to denote that the durations are automatically calculated by P3.
  2. 0
    Paul Naughton ·
    Or, to keep it simple.

    A hammock summarises task activities (using the criteria provided by Praves)
  3. 0
    Marcio Sampaio ·
    Hello Paul and Praves

    Thanks a lot.

    Regards.

    Marcio Eduardo.
  4. 0
    Marcio Sampaio ·
    Hello all.

    Read this other response.

    From Primavera:

    Define a task activity. P3 schedules a task activity according to
    the base calendar assigned to the activity. Designate an
    activity as a task activity if you aren’t assigning resources to the
    activity, or if the assigned resources should be scheduled
    according to the activity’s base calendar; rather than each resource
    calendar.
    For example, several activities must be done in the week before a new
    radio station begins broadcasting. It doesn’t matter
    whether the resources are available earlier than that week, or
    whether they will otherwise be scheduled for time off during
    that week--these activities must be scheduled during a specific
    timeperiod, and their scheduling controls the scheduling of
    their resources.

    Define a hammock activity. Use hammocks to monitor the elapsed
    beginning-to-end duration of a group of activities. A
    hammock duration is the number of days between the beginning of the
    first activity and the end of the last one in the
    group--not the sum of the activities’ durations. If several hammocked
    activities overlap, the hammock’s duration will be smaller
    than the combined durations; if large gaps exist between the
    activities in the hammock, its duration may be longer.

    To set up a hammock activity

    1 Display the Predecessors form for the hammock activity.
    Define the hammock’s predecessors. Specify a start to start
    relationship and zero lag for all predecessors to the hammock.
    2 Display the Successors form for the hammock activity. Specify
    a finish to finish relationship and zero lag for all
    successors to the hammock.
    3 After you establish the beginning and ending points of the
    hammock, calculate the schedule.

    Regards.

    Marcio Eduardo
    Rio de Janeiro - Brazil