Weighted % of activities
In the Open Standard
Alexander BernardoMember for 21 years
- Created
- 5
- 1
0
The schedule was prepared at excel and the equivalent weighted percentage of each activity was calculated accordingly basing on the the cost of each activity (labor and matl).
Now I am preparing at P3 but I can’t produce the desired result i.e. classic layout with weighted percentage to be shown on the report (bar chart).
Please, can somebody guide me how to do that.
Now I am preparing at P3 but I can’t produce the desired result i.e. classic layout with weighted percentage to be shown on the report (bar chart).
Please, can somebody guide me how to do that.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?