Resources Loading (P3)

Redzuan SamsudinMember for 20 years 3 months
Created
2
1
0
Good day to all

I just started to use P3. Previously use MSP98/2K. How do I view Resource Loading in P3.

In MSP, I use : VIEW|REPORTS|WORKLOADS|RESOURCE USAGE (Crosstab : Resources - Peak unit).

I tried in P3 by using : TOOLS|RESOURCES|LOADING|RESOURCES LOADING - BY DAY

Result : I get different result. Does not show same as MSP. My project plan in hours.

By looking at Resource Profile in P3, it show same result as MSP. How do I extract this info into MS Excel e.t.c..

Thanks a lot.

Redzuan

2 replies

Oldest first
  1. 0
    Christian Adrian De Vera ·
    Hello Redzuan

    You are at the right track for checking/exporting the resource loading however check the Tabs (Resource selection, Format, Selection, Timescale) coz you’re using a template by P3 so the resource selection should equal that of your resources plus the timescale.

    Kind regards,

    Christian
  2. 0
    Redzuan Samsudin ·
    Hi

    Thanks for feedback

    May I have ur e-mail so that I can forward u my query with attachment.

    Thanks again

    Redzuan