HWY1, ( highway widening )

Mimoune DjouallahMember for 20 years
Created
7
1
0
Hi all

I was just looking for the sample example given in P3. HWY1, ( highway widening ) then I remarked all equipment resources use units as day ?

Usually we use hours for equipment as sometimes we work more then 8 hours (overtime) ?
Any idea ?

mimoune

7 replies

Oldest first
  1. 0
    Hemanth Kumar ·
    Create A Project With Hours Duration
    P3 Default Is Day
  2. 0
    Mimoune Djouallah ·
    Hi expert

    I suppose that my English is so bad that you did not understand the question?

    My question, why for labour he uses hours, and days for equipments ?

    mimoune

  3. 0
    Ronald Winter ·
    I believe that it all has to do with money. You pay for labor by the hour but you rent equipment by the day.
  4. 0
    Mimoune Djouallah ·
    thanks Ronald


    Ah ok, in our country we even rent equipment by hours!

    mimoune
  5. 0
    Alex Wong ·
    mimoune,

    so if you only use the equipment for 2 hrs do you pay for 2hrs or the whole day??

    Al
  6. 0
    Tahir Naseem PMP, CCE ·
    Yes Mr alex
    It is normal where you have industrial states. For day to day maintenance and specially during the shutdowns. Lot of equipemnt supply you the equipmemnt on hour rate + mob & demob cost. But in this case the rate is abvous high teh daily/weekly/monthly bases.
  7. 0
    Mimoune Djouallah ·
    Hi alex

    Of course it our fault then, we pay him for 8 hours, as we plan to use equipment like truck for 8 hours per day, but if we work for 14 hours we pay him consequently

    mimoune

Log in or join to reply