Hi, Good day,

Please can anyone tell me how to use Blank Column in P3. I introduced one such column but cannot add any data.

Angyan

4 replies

Oldest first
  1. 0
    Hannes de Bruyne ·
    Thats what the word says: if you add data, it would not be a blank column anymore.
    If you want a clolumn without a name in the header this would be a different approach. Than create a column with a name "x" and try to format it in such a way, that you dont see the columns name.
  2. 0
    Tahir Naseem PMP, CCE ·
    Dear ANGYAN
    Would you like to explain for what purpose you want to use this blank coulmn such as for text, numeric, date etc.
    Then may be you can find some help
    Thanks
    Tahir
  3. 0
    Jagathnarayanan ANGYAN ·
    Hi,
    We use the custom DATA and add columns but I was think of using these also mostly for Text.

    Thanks
    Angyan
  4. 0
    Tahir Naseem PMP, CCE ·
    Dear
    No this is for all use. You please follow the following steps and hope you can creat custom data Item as per your choice.
    click Data
    2 custom data item
    3 Give the name of column
    4 clikc the type and here you find , c- character, S- start date, f-finish date, n-numeric, and p-precision

    Regards
    Tahir

Log in or join to reply