How P3 is calculating % complete.....

Reynaldo Y. Calayo Jr.Member for 23 years 7 months
Created
5
6
0
hi guys!

i need some info on how p3 is calculating its % complete.

how it is computing % complete when you run schedule & when you roll up the activities.......

what is the most acurate method in calculating % complete in P3.....

tnx in advance c",)

5 replies

Oldest first
  1. 0
    Mk Tse ·
    According to P3 manual, PCT is "The proportion of an activity that has been completed".
    PCT=[(OD-RD)/OD]x100%
  2. 0
    Mk Tse ·
    When do summary, summarized PCT=
    [(SumOfOD - SumOfRD)/SumOfOD]x100%
  3. 0
    Ronaldo Quilao ·
    Dear Rey,

    How you doing?

    Try to check AutoCost Rule. You can click whichever fit to your requirements in calculation.

    Regards,

    Ronald
  4. 0
    Prabin Kumar ·
    Hi Ray,

    P3 calculates % complete by calculating the percentage of actual duration wrt Total duration. i.e (OD-RD)/OD

    However, if you dont want to use this rule, you can remove the linkage by Autocost rule, But in that case you have to feed % completion and Remaining Duration manually.

    Yes, we can set % completion for summerized activity (Tool >Option>summerization)in three way i.e. by Duration, Resources unit and cost.
    and even you can set different method for different section if you are using more than one calander in your project.


    Thanks


    Prabin Kumar
  5. 0
    Reynaldo Y. Calayo Jr. ·
    hi ronald how are you nice to hear from you.......

    i have done that already what all of you have mentioned
    i even ask some planners here also.....

    let me rephrase my question......
    if i will summarize all the activities the % complete lets say 67% complete
    if i would schedule the programme it will show 57% why there is a difference.......i keep on encountering this problem

    do i have to ask my boss to renew the license??? do i have to replace my PC??? :)


    follow up question......
    lets say i have a delay of 8% on the over all programme i would like to know what % of the overall delays is the blockworks alone????

    tnx in advance guys :)