What is TURNER BREAKDOWN ???

Sami Abu al HeijaaMember for 20 years 1 month
Created
6
1

6 replies

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    are you asking about turnaround?
  2. 0
    Sami Abu al Heijaa ·
    actully i have got a note from the consultant to make a turner brake down for some activites of my schudule so I need to know what is that if posible


    thanks


    sami
  3. 0
    Aneesuddin Zubair Mohammed ·
    Hi,

    It sounds like a language issue rather than a technical/planning!!!!

    Daya, you could find something close to it.

    Regards,

    Anees
  4. 0
    Dayanidhi Dhandapany ·
    you have to break down the item further(whatever it may be turner or burner) in order to show its details as per the consultant’s request so that the items broken down can be easily manageable.
  5. 0
    Ronald Winter ·
    I believe that he must of said, "Further Breakdown."

    This means that you must add in more detail, make activities shorter and add in relationships. For example, no activity should have more than one primary resource, or no activity should include the work of two different companies. Good luck!
  6. 0
    Sami Abu al Heijaa ·
    thanks roald it was like that actully i talkrd to consulntant and he clreified this issue


    tahnks for all you were helpfull

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?