Increase SDK Speed

Bishop OConnellMember for 19 years 11 months
Created
0
2
0
Just an FYI for everyone. If you are doing more than one project in SDK the time it takes will increase exponentially for each project. For example we had 8 projects we were using. If we brought the resource spreads over those 8 would take 1-1.5 hours to run. Doing each one on it’s own takes 20-30 minutes total. HUGE difference. I know API is faster but I wanted to make sure everyone knew this option as it might help if SDK is your only option. Even Primavera didn’t know this.