WBS

Likaa LikaaMember for 20 years 4 months
Created
5
1
0

Hi,

I Want to Repet WBS Struture for 1 floor To Another Mean I want to copy the same Title but in another code,I Want to Organized in wbs way. Any body can help me to do it fast because its delay me when i typed again & again.



thanks,

Likaa

5 replies

Oldest first
  1. 0
    Alex Wong ·
    export your activity list with wbs
    copy and paste in Excel for all the wbs no
    import back to p3

    hth

    alex
  2. 0
    John Raper ·
    Likaa

    Select the WBS code you wish to copy, then paste it. Simple!
    P3 will ask for a new code value for the copied part.
  3. 0
    Paul Harris ·
    The copy function in the WBS form is designed to copy an arm of a WBS structure.

    The is also a Excel spreadsheet available that may be used to import and export WBS Codes and Descriptions available from the P3 web site under Solution ID: 200252492644.

    The other option is to use Batch but the spreadsheet is a lot simpler.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  4. 0
    Mohamed Thabet ·
    Hi Paul,

    First i would like to thank you for your book "Planning & scheduling using p5" it made it simple to me.

    Can you explain how can i access the spreadsheet from primavera web site ?

    Regards,

    Moe
  5. 0
    Paul Harris ·
    Go to http://www.primavera.com/customer/index.asp and register, you will need a P3 license that is in maintenance to register. After registering you will have access to the database, do a search on the number below and you will be able to download the files.

    This spreadsheet is for P3 Ver 3.1 not Primavera Version 5.0.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au