Skip to content

negative milestone

Moutaz AldeibMember for 22 years 9 months
Created
6
3
0
Dear Planners,

I have start milestone which has total float equal zero, next month no progress, consequently the completion date is shifted "delay" but the total float for the milestone is still zero (I thought it will be negative).
Is this logic?

Thanks

6 replies

Oldest first
  1. 0
    Edgar Ariete ·
    Hi Moutaz,

    you can ask Atef..


    cheers
  2. 0
    Brennan Westworth ·
    The milestone is still on the critical path because its float equals zero, or its early finish is the same as its late finish.

    Negative float occurs when your early finish is after your late finish. To fix the project end date and display variance in terms of float (negative float for over schedule) then apply a late finish constraint to your last activity.
  3. 0
    Moutaz Aldeib ·
    Thanks Brennan, but why for activity has positive total float, and no progress occurs, the total float decreases by approximately one month (updated monthly).

    Regards,

    Moutaz
  4. 0
    Brennan Westworth ·
    Its difficult to answer without knowing the details of your schedule.

    I assume it is the same schedule with a floating end date (ie not late constrained), I also assume that some progress was made on your critical path during the month. (if not then best to look for another job ;))

    therefore the amount of progress made on your critical path will be equal to the reduction in float on the non critical activity you mentioned.
  5. 0
    Santhosh kumar Narayanan ·
    I agree wirh brennan!! better u find a job!!..

    The reason being the predecessor not finihsed as per planned and pushed the successor activity one month(in ur monthly update) and consumes the float.. simple my dear!! plz study closly the links !!

    Thanks
  6. 0
    Marcio Sampaio ·
    Total float is calculated from the end to begin of project. It means that if it delay 1 day, the project will delay 1 day. That is why it is still zero.

    Regards.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?