negative milestone
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 6
- 3
0
Dear Planners,
I have start milestone which has total float equal zero, next month no progress, consequently the completion date is shifted "delay" but the total float for the milestone is still zero (I thought it will be negative).
Is this logic?
Thanks
I have start milestone which has total float equal zero, next month no progress, consequently the completion date is shifted "delay" but the total float for the milestone is still zero (I thought it will be negative).
Is this logic?
Thanks