Planning Schedule of Pipe Fabrication
In the Open Standard
Syed Shahzad Hussain ShahMember for 20 years 1 month
- Created
- 2
- 2
0
Dear All,
Any one can guide me regarding the preparation of schedule of Piping Fabrication in Fabrication Shop.
For example when we prepare a schedule for a pressure vessel we add activities like
1. Plate cutting aas per drawing
2. Rolling
3. Fitup
4. Rerolling
5. Welding
7. Nozzels cutting
6. Fitup of ends
& so on this is information belongs to limited drawings say 01 to 10, but in Pipie fabrication we will based on each dia inch of pipe in each drawing or we will go general as cuuting, fitup, welding, rt & so on.
I want to prepare a shedule for pipe fabrication of 75000 dia inches & these dia inches related to 500 drawings, if i will go for each drawing separatly the total taskes may go above 20000, which are some what difficult to manage.
Regards,
SHAH
Any one can guide me regarding the preparation of schedule of Piping Fabrication in Fabrication Shop.
For example when we prepare a schedule for a pressure vessel we add activities like
1. Plate cutting aas per drawing
2. Rolling
3. Fitup
4. Rerolling
5. Welding
7. Nozzels cutting
6. Fitup of ends
& so on this is information belongs to limited drawings say 01 to 10, but in Pipie fabrication we will based on each dia inch of pipe in each drawing or we will go general as cuuting, fitup, welding, rt & so on.
I want to prepare a shedule for pipe fabrication of 75000 dia inches & these dia inches related to 500 drawings, if i will go for each drawing separatly the total taskes may go above 20000, which are some what difficult to manage.
Regards,
SHAH
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?