Update Progress for Look Ahead Schedule
In the Open Standard
Siva KumarMember for 21 years 3 months
- Created
- 1
- 2
0
Hello all
Generally for preparing Look ahead schedules,we fix the target from the updated programme of works and update the progress of that file to the required data date to project the progress for one week or month ..
The problem is ,some activity gets updated and some get reduced in % complete or get zeroed ..eventhough progress override is enabled.
Is there any solution for this..
Regards
Kumar.
Generally for preparing Look ahead schedules,we fix the target from the updated programme of works and update the progress of that file to the required data date to project the progress for one week or month ..
The problem is ,some activity gets updated and some get reduced in % complete or get zeroed ..eventhough progress override is enabled.
Is there any solution for this..
Regards
Kumar.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?