MPP to P3 (advanced)
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 9 months
- Created
- 2
- 22
0
Hello all,
when importing some ms project files into p3, we find a INTRUSIVE lag in the relationship between the last and one-before-last activities in the P3 project;
this lag does not exist in the MPP file and cannot be seen in the MPX file;
the same occurs if we use the Primavera Corp MPPtoMPX converter or the Sciforma MPX2K converter, but does not when we create the MPX file directly from Sciforma PS8;
we are using P3 (do not yet if SP2/SP3 is installed) on a Windows XP Pro SP1 or SP2 plateform.
Does somebody have an idea?
Thanks,
Alexandre
P.S. I will send the files on request
when importing some ms project files into p3, we find a INTRUSIVE lag in the relationship between the last and one-before-last activities in the P3 project;
this lag does not exist in the MPP file and cannot be seen in the MPX file;
the same occurs if we use the Primavera Corp MPPtoMPX converter or the Sciforma MPX2K converter, but does not when we create the MPX file directly from Sciforma PS8;
we are using P3 (do not yet if SP2/SP3 is installed) on a Windows XP Pro SP1 or SP2 plateform.
Does somebody have an idea?
Thanks,
Alexandre
P.S. I will send the files on request
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?