Progress in Primavera schedule
In the Open Standard
vasudevan DhakshinamoorthyMember for 19 years 7 months
- Created
- 12
- 3
0
I am recently done a schedule in Primavera for a power plant project. I have sucessfully made the project schedule with assigning the base line. I got into a bit of trouble while entering the progress of each activity. I entered 100% completion for activity-1 and scheduled by pressing F9. The next activity date of start shifted earlier even though the start of that activity is after 10 to that of finish of activity-1.
any one can suggest to rectify
Vasudevan