cascade of activities without logic

Jonathan WardMember for 19 years 8 months
Created
2
1
0
Hi,
once again another question that i’m sure you will be able to answer without thinking,,, i have a list of activities that have no logic connecting them, i would like to view these activities in a cronological order (have them cascasde down the page, earliest date first etc), can P3 do this for me, when i re-schedule at the moment, the activities are listed in order of Activity ID
once again
thank you very much for your help
regards
Jon

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Jon,

    Yes you can organize and sort them by early start date.
    Goto Format-> Organize... on your P3 menu
    On Sort By box click Activity Id and change it to Early Start then Click Organize Now.

    You can add as many sorting your require.

    Rodel
  2. 0
    Jonathan Ward ·
    once again
    thank you for your kind help
    best regards
    jon